Just One More Sprint !?
▻https://hackernoon.com/just-one-more-sprint-9832c11cf9b3?source=rss----3a8144eabfe3---4
In this post I am going to use a common scenario to highlight some key product development prioritization concepts. Specifically, we are going to dig in to the decision to stop one effort, and start another effort.Do We Keep Going?Let’s start with an example. When I draw it out below, you might say “this is a no brainer!” On some level it is, but stick with me.Example…I think a new workflow will generate $45k in extra revenue monthly (the Cost of Delay). We work for two weeks, and realize some very high percentage of that value ($42k/month). Should we “finish the project” (in this case add an additional option to the workflow), or should we stop immediately and take on new work?Note how there is $3k left on the table…it is value yet to extract.Comparing CD3 (For Work Done, and Work (...)