• USS Ford Munitions Elevators Miss Another Deadline in HII Setback - Bloomberg
    https://www.bloomberg.com/news/articles/2019-07-30/flawed-elevators-on-13-billion-carrier-miss-another-deadline


    The $13 Billion USS Gerald Ford Plagued by Problems

    • ‘Essentially, the ship can’t deploy,’ lawmaker Luria says
    • Weapons can’t be lifted to the deck of USS Gerald R. Ford

    Only two of 11 elevators needed to lift munitions to the deck of the U.S. Navy’s new $13 billion aircraft carrier have been fully installed, according to a Navy veteran who serves on a key House committee.

    I don’t see an end in sight right now” to getting all the elevators working on the USS Gerald R. Ford, the costliest warship ever, Democratic Representative Elaine Luria of Virginia said in an interview. The ship was supposed to be delivered with the Advanced Weapons Elevators, which are moved by magnets rather than cables, working in May 2017.

    It’s another setback for contractor Huntington Ingalls Industries Inc. — and for the Navy, which had said in December it planned to complete installation and testing of all 11 elevators before the Ford completed its post-delivery shakedown phase this month, with at least half certified for operation.

    Instead, the shakedown phase has been extended to October and the vessel won’t have all the elevators fully installed — much less functioning — by then, according to Luria, a 20-year Navy surface warfare officer whose served on two aircraft carriers and as shore maintenance coordinator for a third.

    Essentially, the ship can’t deploy,” Luria said. “It can’t carry ammunition.” She said the Navy and Huntington Ingalls are trying to solve new problems with doors and hatches lining elevators shafts that don’t meet specifications.